The Genesis field is located 150 miles south of New Orleans, across the three
Green Canyon blocks 160, 161 and 205. The water depth varies from 2,500 to 3,000ft.
The Genesis production facility is moored in 2,600ft of water.
The Genesis field is located 150 miles south of New Orleans, across the three
Green Canyon blocks 160, 161 and 205. The water depth varies from 2,500 to 3,000ft.
The Genesis production facility is moored in 2,600ft of water.

RESERVES

Genesis lies in the Viosca Knoll Carbonate Trend. The field contains reserves
of 160 million bbl. Following drilling, flow tests were conducted in which the
field produced at rates of up to 8,300bbl/day. Production will peak at about
55,000bbl of oil and 72 million ft³ of natural gas per day.

ENGINEERING

The engineering design and procurement was handled in two phases. The front-end
engineering (FEE) included the preparation of installation plans, electrical
lines, equipment arrangement and cost estimates. The detailed engineering phase
included the deck’s structural design, piping, electrical and instrumentation
design, requisition, inspection and hook-up through to start-up.

DEVELOPMENT

Genesis is being developed using a cylindrical steel spar, which supports both
the drilling operations and production facilities. This makes it the world’s
first drilling/production spar. Air-filled compartments on the upper portion
of the cylinder provide buoyancy, while seawater-filled tanks on the bottom
give weight and stability.

TOPSIDES

Fabrication of the platform’s deck was carried out at McDermott’s
Morgan City facility in Louisiana. Engineering was provided by McDermott Engineering
Houston. The topsides have a deck surface area of about 100,000ft² (three
175ftx175ft levels) and a loadout weight of approximately 9,000t.

The topsides consists of 5,150t of structural steel, 2,600t of production equipment
and 945t of interconnecting piping, electrical lines and instrumentation. The
fabrication contract includes mechanical completion, commissioning, loadout
and tiedown.

The Genesis topsides were fabricated as two units – the production deck and
the drill/utility deck. Prior to loadout, the drill/utility deck was cut into
two pieces (between truss rows one and two) to facilitate movement.

HULL

The Genesis hull is 122ft in diameter and 705ft tall. It was manufactured in
two halves at Aker Rauma’s Pori yard, in Finland. The first half, weighing 10,842t
was sailed to Corpus Christi two months before the second 15,861t-half, using
Dockwise’s submersible lift vessel, Transshelf. The hull incorporates a 58ftx58ft
well bay at its centre, which is enough for 20 well slots.

INSTALLATION

The spar installation was carried out by McDermott’s Derrick Barge 50 in three
phases: the mooring system, the hull and the topsides. The platform is held
in place with a 14-point mooring system.

Each line is composed of 250ft of 5.25in-diameter anchor chain, 3,000ft of
5.25in-diameter wire rope and 1,150ft of hull chain. An anchor pile/hammer assembly,
attached to the chain and mooring wire, was lowered to the seafloor. These mooring
piles had a loadout weight of 3,590t. Each mooring pile was 8ft outside diameter
and 235ft long.

Following this, the hull was brought into the field. Approximately 178,000t
of water ballast was introduced in a staged free flooding to upend the hull.
The final stage of upending, which rotated the hull through over 70°, took
only 76sec.

The hull was then positioned near the centre of the mooring pattern. The 14
mooring lines were attached to the chain jacks on the hull from a temporary
work deck.

RISERS

The riser system consists of the production, export and drilling risers, all
run with a platform drilling rig. The complete system analysis involved complex
analytical modelling of the individual components and the interface with the
spar.

The spar can support up to 20 production risers, two export pipeline risers
and one drilling riser. Each is approximately 2,650ft long up to the span, from
seafloor wellheads to the topsides. The 20 subsea wellheads and two export riser
bases on the seafloor are arranged in a 140ft-diameter circle, with 20ft of
spacing.

To see pictures, dowload : genesis.zip
from : http://www.offshore-technology.com/projects/genesis/